Extensive modernisation work is currently being carried out at the AOK Stadion. With a view to the upcoming season, not only is the playing surface being renewed, but the infrastructure beneath the pitch is also being further developed. However, a project of this kind involves far more than simply laying a new pitch. In this interview, Jan Naumann, Head of Groundskeeping at VfL Wolfsburg, discusses the current work, the challenges of a project on this scale and the importance of modern stadium infrastructure.
Jan Naumann, anyone looking into the AOK Stadion at the moment can immediately see that work is underway. What measures are currently being implemented?
Jan Naumann: The pitch is currently undergoing a comprehensive modernisation. In addition to the complete renewal of the turf, it is being converted to a hybrid pitch system. Work is also being carried out on the substructure. This includes the installation of foam glass aggregate to improve the facility’s energy efficiency and reduce energy costs over the long term.
Why was the pitch renewal scheduled for this particular time?
Jan: The summer break provides the ideal window for measures of this scale. This allows the work to be carried out without disrupting football operations, and the stadium will be ready in optimal condition in time for the start of the season.
How long does the preparation for a project of this scale normally take?
Jan: Projects like this are planned many months in advance. From the initial needs analysis and coordination with specialist planners and contractors through to detailed scheduling, numerous steps are required to ensure the project runs smoothly.
Which departments and teams are involved in the work?
Jan: Various specialist departments are working closely together on the project. These include Facility Management, Groundskeeping, STRABAG, external sports turf construction companies and other technical service providers. Close coordination between all parties involved is essential.
What are the biggest challenges in a project like this?
Jan: The greatest challenge is implementing all measures within a tight timeframe while maintaining the highest quality standards. In addition, factors such as weather conditions, material availability and the coordination of different trades all play a role.